Project Goals and Timeline

The finished system must have the following functions:

Additional Requirements:

Timeline:

Goal

Estimated Completion Date

Investigation of current system

Complete  (9/24/2012)

Removal of non-functional components

Complete (9/24)

Begin initial control system design

Complete (9/24)

Determine control system hardware

Complete (10/1)

Begin power supply design

Complete (10/29)

Implement control system with base functionality

Complete (11/16)

Implement power supply

Complete (12/14)

User interface design

Complete (12/14)

Breadboarded prototype Complete (2/11/2013)

PCB design and order

Complete (Over spring break)

Functional system 4/15
Design fair 4/25