DateDescirption
8/29-9/15Theoretical Calculation and Research
9/15-10/25Experiment Design and Optical Design Reiterations
10/26-11/22Computer Hardware Interface
11/23-12/09Final Design/Report (Ordering Parts)
12/09-2/15Construction, Electronics and Optical Layout
1/4-1/10Horizontal Stage, Dectector/Data Acquisition System
1/11-1/18Gating Mount and Support, Motor Electrical System
1/19-1/26Motor Guides, Assemble Linear Motor System, General Electrical
1/26-2/1Spectrograph Case and Lens PVC Mounts, Computer Interface
2/2-2/9Spectrograph Case Legs, Validate Electrical System
2/10-2/15Wiggle Room, Finalize Computer Interface and Functionality
2/15-3/1Testing / Calibration
3/2-4/15Implementation - Performing experiments and analyzing results
4/15-5/4Final Report/Presentation
5/16-5/19NSSSC Final Competition!